Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%

Progress in construction RC “SHCHASLYVYI” Lviv, May 2024

The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:

• installation of waterproofing of the floor in the basement, cement-sand screed in the storerooms and common corridors of the basement;

• installation of electricity in the lobby of the house;

• laying of electrical cables in the building from the basement to the 17th floor (power supply for elevators, electrical panels on the floors);

• installation of lighting fixtures in the stairwells and installation of lighting fixtures in the corridors of the public usage places (10-17 floors);

• installation of gas boilers and heating radiators (10-17 floors);

• insulation of the 1st floor facade has begun;

• painting and varnishing of decorative plaster on the walls of the public usage places (4-7 floors);

• ceramic tiling of stairwells (1-3 floors) and floors of the public usage places (6-7 floors);

• installation of Armstrong suspended ceilings in the public usage places (4-5 floors);

• installation of electrical cabinets with meters (2-6 floors);

• framing of elevator portals for two elevators (1-17 floors);

• installation of fire extinguishing and warning systems (floors 2-17).