1
stage
100%
The first two buildings of the residential complex have been commissioned, and the construction of the third building is underway:
• installation of window sills on floors 2-17;
• installation of public usage doors and hanging of fittings on floors 2-17;
• installation of window structures on the 1st floor;
• tiling of cold passages balconies on floors 2-17;
• tiling of the staircase on the 16-17 floors;
• finishing works on 12-17 floors;
• installation of a freight elevator;
• masonry partitions of the kindergarten on the 1st floor.