Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%

Progress in construction RC “SHCHASLYVYI” Lviv, August 2023

The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:

• installation of the horizontal formwork of the floor slab above the parking lot; the reinforcement twisting of the floor slab has begun;

• brickwork of partitions for storerooms in the basement;

• pouring screed on 5-8 floors;

• arrangement of the wet facade of the chimneys on the roof (reinforcement and application of texture);

• the arrangement of the ventilated facade is completed.