1
stage
100%

The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• installation of the horizontal formwork of the floor slab above the parking lot; the reinforcement twisting of the floor slab has begun;
• brickwork of partitions for storerooms in the basement;
• pouring screed on 5-8 floors;
• arrangement of the wet facade of the chimneys on the roof (reinforcement and application of texture);
• the arrangement of the ventilated facade is completed.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: FEBRUARY 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
28.02.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (FEBRUARY 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
28.02.2026
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: FEBRUARY 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.