The first two houses of the RC have been commissioned, construction of the third house proceeds:
• monolithic works on the third building of the residential complex are completed;
• work on the masonry of the external walls is gradually approaching the final (it lasts on the 11th and 14-17 floors);
• sewer elements are currently being installed (vertical risers are almost ready - by 75%);
• a fire water supply system is being installed for the house;
• ventilation ducts and smoke extraction system will be ready within 10 days;
• preparation for the start of work on the underground parking pit is coming to an end.