The first two houses of the residential complex have been commissioned, the construction of the third one proceeds:
• the installation of the floor formwork above the 12th floor is nearing completion. After that, the pouring of this slab will begin soon;
• masonry of walls from the first to the fourth floor inclusive is in the active process;
• chimneys and ventilation shafts are being installed along with the masonry of the walls. It is important that these stages occur simultaneously in order for the house to have a perfect system of air supply and exhaust;
• waterproofing of the basement walls is being created;
• preparation for installation of sewer risers has been completed, work on which will begin soon;
• work on the waterproofing of the underground parking lot is underway.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025