The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• concreting of the floor slab above the parking lot;
• pouring screed on 3-5 floors;
• drilling holes for gas risers in apartments;
• arrangement of wet facade on chimneys and roof (completed);
• production of blanks for laying gas pipes in apartments;
• arrangement of window drains;
• arrangement of a wet facade on cold transitions - gluing of mineral wool;
• laying of power electric cables from transformer substation to switchboards of the 3rd building.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026