The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• concreting of the floor slab above the parking lot;
• pouring screed on 3-5 floors;
• drilling holes for gas risers in apartments;
• arrangement of wet facade on chimneys and roof (completed);
• production of blanks for laying gas pipes in apartments;
• arrangement of window drains;
• arrangement of a wet facade on cold transitions - gluing of mineral wool;
• laying of power electric cables from transformer substation to switchboards of the 3rd building.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: FEBRUARY 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
28.02.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (FEBRUARY 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
28.02.2026
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: FEBRUARY 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
24.02.2026