The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• concreting of the floor slab above the parking lot;
• pouring screed on 3-5 floors;
• drilling holes for gas risers in apartments;
• arrangement of wet facade on chimneys and roof (completed);
• production of blanks for laying gas pipes in apartments;
• arrangement of window drains;
• arrangement of a wet facade on cold transitions - gluing of mineral wool;
• laying of power electric cables from transformer substation to switchboards of the 3rd building.