The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• installation of railings of cold transitions, stairwells and stairs to the basement;
• masonry of storerooms in the basement;
• the first stage of welding and installation of gas pipes in apartments;
• arrangement of the wet facade of the 1st floor ceilings;
• concreting of two entrance groups to the house;
• waterproofing of cold passages floor;
• arrangement of screed (except basement);
• installation of drippers for cold transitions balconies and window ebbs of the house;
• installation of freight elevator equipment;
• decoration of cold passages balconies with ceramic tiles;
• installation of plasterboard boxes under shields on floors 12-17;
• puttying of the public usage places walls on the 13th-15th, 17th floors;
• installation of public usage places doors;
• installation of horizontal formwork under the floor slab in the underground parking lot;
• unfolding and knitting the reinforcement of the floor slab in the underground parking lot.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.