The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• installation of railings of cold transitions, stairwells and stairs to the basement;
• masonry of storerooms in the basement;
• the first stage of welding and installation of gas pipes in apartments;
• arrangement of the wet facade of the 1st floor ceilings;
• concreting of two entrance groups to the house;
• waterproofing of cold passages floor;
• arrangement of screed (except basement);
• installation of drippers for cold transitions balconies and window ebbs of the house;
• installation of freight elevator equipment;
• decoration of cold passages balconies with ceramic tiles;
• installation of plasterboard boxes under shields on floors 12-17;
• puttying of the public usage places walls on the 13th-15th, 17th floors;
• installation of public usage places doors;
• installation of horizontal formwork under the floor slab in the underground parking lot;
• unfolding and knitting the reinforcement of the floor slab in the underground parking lot.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.