Progress in construction RC “SHCHASLYVYI” Lviv, October 2019

Here we are talking about the progress of construction of residential complex "Shchaslyvyi" in Lviv, located by address 17, Bihova St.

Work is currently underway to install gas equipment in the house. So the communications are almost ready. The work on the decoration of the hall is also almost finished. The framing of the elevator shafts has been completed, and the cleaning has started in the corridors.

Separate about the facade: the wet facade on the side of the building facing the High Castle has already been completed by 80%. And the facade is ready for more than 50% on the ground floor.

At the same time, the landscaping around the second stage is coming to an end. It will be closed from strangers, and you can see that 90% of the fence is ready right now .

The paving has been started, which will make the road around the house. So don't waste your time! The work being done now is the final part of construction. The house is almost ready, but the price has not risen yet.