100%
The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• facade works continue, in particular, the arrangement of the wet facade (70% completed) and the ventilated facade (75% completed);
• craftsmen are engaged in covering chimneys on the roof, which will be completed by March 20, and covering parapets;
• pavers have been laid in the backyard near the second house.