The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:
• all finishing works on the 1st-17th floors have been completed;
• finishing works in the basement;
• insulation of the facade of the 1st floor (70% complete);
• installation of a pumping station in the building for the needs of residents (50% complete);
• installation of electrical panels in the apartments;
• installation of radiators (4-7 floors);
• installation of gas boilers (8-10 floors);
• installation of suspended ceiling, installation of doors and windows in the lobby.