The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:
• all finishing works on the 1st-17th floors have been completed;
• finishing works in the basement;
• insulation of the facade of the 1st floor (70% complete);
• installation of a pumping station in the building for the needs of residents (50% complete);
• installation of electrical panels in the apartments;
• installation of radiators (4-7 floors);
• installation of gas boilers (8-10 floors);
• installation of suspended ceiling, installation of doors and windows in the lobby.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026