Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%

Progress in construction RC “SHCHASLYVYI” Lviv, June 2024

The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:

• all finishing works on the 1st-17th floors have been completed;

• finishing works in the basement;

• insulation of the facade of the 1st floor (70% complete);

• installation of a pumping station in the building for the needs of residents (50% complete);

• installation of electrical panels in the apartments;

• installation of radiators (4-7 floors);

• installation of gas boilers (8-10 floors);

• installation of suspended ceiling, installation of doors and windows in the lobby.