100%
The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• plumbing works on the rolling of cold water and heating pipes on floors 13-17 have been completed;
• plastering works on the 3rd, 5th, 7th, 8th, 11th floors have been completed;
• arrangement of chimney covers is in progress;
• the wet facade is completed.