Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%

Progress in construction RC “SHCHASLYVYI” Lviv, July 2022

The first two houses of the residential complex were commissioned, the construction of the third one continues:

• window glazing has been carried out;

• an external gas network in the house has been conducted ;

• an external network - sewerage and drainage sewerage has been put;

• installation of internal electrical networks on floors 2-16 of the complex;

• the road is being arranged from the side of Trakt Hynansky Street;

• the start of the roof construction, interior plastering and facade work is planned.