The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:
• concreting of the bowl for the fountain;
• finishing of the floor and walls of the basement corridors has been completed;
• installation of equipment for domestic and fire pumping stations in the building has been completed;
• cold water pipelines have been laid to the premises of the 1st floor;
• installation of doors in the basement to the pump room, electrical room, and fan room;
• landscaping works along the building to the entrance to the hall and from the end of the building;
• tiling of the 1st floor facade has been completed;
• finishing of the hall, installation of mailboxes;
• hanging bars in the places of fire valves installation;
• cleaning of the public usage premises and the hall.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025