The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• pouring screed on floors 9-13;
• pouring vertical elements of the parking lot;
• welding of the water pipeline of the house, laying of pipes to the pumping station;
• distribution of cold water and heating pipes in apartments;
• arrangement of a wet facade in the place where the crane stood;
• plastering funnels with mineral wool on the roof.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026