The first two houses of the RC have been commissioned, the construction of the third house proceeds:
• a monolithic slab has been poured over the 16th floor;
• masonry in ventilation shafts up to and including the 12th floor is completed;
• sewer risers and chimneys are also laid up to and the12th floor including;
• masonry of walls and partitions from 6 to 10 floors inclusive continues.