
The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:
• pouring screed on the 15th floor;
• concreting of vertical parking elements;
• arrangement of sewage in the basement;
• welding of indoor water supply pipes, pipes laying to the pumping station;
• plumbing works for the distribution of heating and cold water pipes on 2-3 floors;
• during this month, it is planned to complete the ventilated facade, complete plumbing works (laying of cold water and heating pipes in apartments, connection of sewage to external networks), pour the screed on floors 11-14, continue work in the underground parking lot.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025