Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%

Progress in construction RC “SHCHASLYVYI” Lviv, June 2023

The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:

• pouring screed on the 15th floor;

• concreting of vertical parking elements;

• arrangement of sewage in the basement;

• welding of indoor water supply pipes, pipes laying to the pumping station;

• plumbing works for the distribution of heating and cold water pipes on 2-3 floors;

• during this month, it is planned to complete the ventilated facade, complete plumbing works (laying of cold water and heating pipes in apartments, connection of sewage to external networks), pour the screed on floors 11-14, continue work in the underground parking lot.