The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:
• waterproofing of the parking lot walls has been completed;
• installation of gas pipes around the building has been completed;
• tiling of the floor in the public usage places (6, 7 floors);
• application of decorative plaster on the walls of the public usage places (7-9 floors);
• puttying of the public usage places walls and stairwells (2-7 floors);
• installation of fire alarm cables (5-10 floors);
• installation of electrical cabinets with meters (7-17 floors);
• installation of electrical cables;
• filling the ceilings with Armstrong cassettes (10-17 floors);
• restoration of the studded membrane around the building, sanding around the building to the bottom of the landscaping pie;
• preparing for the installation of water combs and batteries in the house.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025