Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%

Progress in construction RC “SHCHASLYVYI” Lviv, July 2024

The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:

・ceramic tile flooring in the basement;

・painting the basement walls in common corridors;

・finishing the walls and floors of the stairwells to the basement;

・installation of equipment in the electrical control room;

・installation of equipment for domestic and fire pumping stations in the building;

・laying of electric power supply cables for commercial premises on the 1st floor;

・ tiling of the 1st floor facade;

・ installation of fire valves (2-17 floors);

・ commissioning of two elevators;

・finishing works in the lobby;

・installation of gas boilers (2-9 floors);

・ installation of radiators (2-5 floors);

・ landscaping works at the entrance.