The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:
・ceramic tile flooring in the basement;
・painting the basement walls in common corridors;
・finishing the walls and floors of the stairwells to the basement;
・installation of equipment in the electrical control room;
・installation of equipment for domestic and fire pumping stations in the building;
・laying of electric power supply cables for commercial premises on the 1st floor;
・ tiling of the 1st floor facade;
・ installation of fire valves (2-17 floors);
・ commissioning of two elevators;
・finishing works in the lobby;
・installation of gas boilers (2-9 floors);
・ installation of radiators (2-5 floors);
・ landscaping works at the entrance.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025