The first two houses of the residential complex have been commissioned, and the construction of the third one is underway:
・ceramic tile flooring in the basement;
・painting the basement walls in common corridors;
・finishing the walls and floors of the stairwells to the basement;
・installation of equipment in the electrical control room;
・installation of equipment for domestic and fire pumping stations in the building;
・laying of electric power supply cables for commercial premises on the 1st floor;
・ tiling of the 1st floor facade;
・ installation of fire valves (2-17 floors);
・ commissioning of two elevators;
・finishing works in the lobby;
・installation of gas boilers (2-9 floors);
・ installation of radiators (2-5 floors);
・ landscaping works at the entrance.