Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%

Progress in construction RC “SHCHASLYVYI” Lviv, March 2024

The first two houses of the residential complex have been commissioned, and the construction of the third house is underway:

• insulation of the house basement and sanding of the car park and house;

• tiling of the floor in the public usage places (floors 4, 5, 8, 9);

• applying decorative plaster to the walls of the public usage places (10-17 floors);

• installation of inspection hatches on water closets and low-voltage points;

• installation of a passenger elevator;

• installation of the Armstrong suspended ceiling frame (12-17 floors);

• installation of power supply cables for fire systems (fire panels, manual alarm button, in-apartment smoke detectors).