The first two houses of the residential complex have been commissioned, and the construction of the third house is underway:
• insulation of the house basement and sanding of the car park and house;
• tiling of the floor in the public usage places (floors 4, 5, 8, 9);
• applying decorative plaster to the walls of the public usage places (10-17 floors);
• installation of inspection hatches on water closets and low-voltage points;
• installation of a passenger elevator;
• installation of the Armstrong suspended ceiling frame (12-17 floors);
• installation of power supply cables for fire systems (fire panels, manual alarm button, in-apartment smoke detectors).