1
stage
100%
The first two buildings of the residential complex have been commissioned, and the construction of the third building is underway:
• grinding of concrete surfaces;
• laying partitions of the kindergarten (1st floor);
• installation of porcelain tiles on the staircases (12-18 floors);
• puttying of the walls of the public usage places (8-11 floors);
• installation of decorative plaster (11, 12, 16 floors);
• installation of apartment doors (11-17 floors);
• installation of a freight elevator.