Progress in construction

1
stage
100%
2
stage
100%
3
stage
98%

Progress in construction RC “SHCHASLYVYI” Lviv, January 2024

The first two buildings of the residential complex have been commissioned, and the construction of the third building is underway:

• grinding of concrete surfaces;

• laying partitions of the kindergarten (1st floor);

• installation of porcelain tiles on the staircases (12-18 floors);

• puttying of the walls of the public usage places (8-11 floors);

• installation of decorative plaster (11, 12, 16 floors);

• installation of apartment doors (11-17 floors);

• installation of a freight elevator.