The first two buildings of the residential complex have commissioned, the construction of the third building is in progress:
• facade works are ongoing;
• plastering works on the 10th, 14th, 15th floors have been completed;
• chimney covers are installed;
• screed on the roof is completed;
• preparatory work was carried out before soldering the membrane;
• a part of the earthwork for the construction of the road has been completed, the curbs have been installed.