Progress in construction

1
stage
100%
2
stage
100%
3
stage
88%

Progress in construction RC “SHCHASLYVYI” Lviv, September 2021

The first two houses of the RC have been commissioned, the construction of the third house proceeds:

• a monolithic slab has been poured over the 16th floor;

• masonry in ventilation shafts up to and including the 12th floor is completed;

• sewer risers and chimneys are also laid up to and the12th floor including;

• masonry of walls and partitions from 6 to 10 floors inclusive continues.