Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%

Progress in construction RC “SHCHASLYVYI” Lviv, November 2022

The first two buildings of the residential complex have been commissioned, the construction of the third building is in progress:

• plumbing works on the rolling of cold water and heating pipes on floors 13-17 have been completed;

• plastering works on the 3rd, 5th, 7th, 8th, 11th floors have been completed;

• arrangement of chimney covers is in progress;

• the wet facade is completed.