Here we are talking about the progress of construction of residential complex "Shchaslyvyi" in Lviv, located by address 17, Bihova St.
Work is currently underway to install gas equipment in the house. So the communications are almost ready. The work on the decoration of the hall is also almost finished. The framing of the elevator shafts has been completed, and the cleaning has started in the corridors.
Separate about the facade: the wet facade on the side of the building facing the High Castle has already been completed by 80%. And the facade is ready for more than 50% on the ground floor.
At the same time, the landscaping around the second stage is coming to an end. It will be closed from strangers, and you can see that 90% of the fence is ready right now .
The paving has been started, which will make the road around the house. So don't waste your time! The work being done now is the final part of construction. The house is almost ready, but the price has not risen yet.
Call: (067) 663 97 34, (067) 663 97 18. Also welcome to the sales offices in 26, Tchaikovsky Street, and 67, V. Chornovola Ave.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: SEPTEMBER 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.09.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (SEPTEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.09.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.