Progress in construction

1
stage
100%
2
stage
100%
3
stage
88%

Progress in construction RC “SHCHASLYVYI” Lviv, October 2021

The first two houses of the RC have been commissioned, construction of the third house proceeds:

• monolithic works on the third building of the residential complex are completed;

• work on the masonry of the external walls is gradually approaching the final (it lasts on the 11th and 14-17 floors);

• sewer elements are currently being installed (vertical risers are almost ready - by 75%);

• a fire water supply system is being installed for the house;

• ventilation ducts and smoke extraction system will be ready within 10 days;

• preparation for the start of work on the underground parking pit is coming to an end.