REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2026

30.09.2026

We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.

The following stages have been completed in full or in part:

Section 1

• concreting of the vertical elements on the 4th floor;

• concreting of the floor slab above the 4th floor;

• concreting of the vertical elements on the 5th floor (40% complete);

• masonry work on walls and partitions in the basement (90% complete);

• concreting of the foundation for the storage tanks in the basement.

Section 2

• installation of cold-water and heating pipes on floors 2-7;

• installation of a vapor barrier made of Euro-ruberoid on the balconies;

• plastering of the stairwell walls.

Section 3

• plastering the walls on the floors 2-3, the stairwell, and the stairs leading to the basement;

• installing a vapor barrier made of Euro-ruberoid on the balconies on floors 4-7.

Section 4

• installation of a floor screed on floors 2-5.

Intermediate section

• concreting of reinforced concrete elements on the 2nd floor level on the terrace.

Sections 5 and 6

• masonry work on a separate room in the stairwell of Section 5;

• backfilling of the excavation voids near Section 6.

Other types of work

• vertical waterproofing of underground parking lot walls (50% complete);

• plastering of walls and partitions in the underground parking lot within 2-3 sections;

• masonry work on walls and partitions in utility rooms and restrooms in the underground parking lot.

Further works include:

Section 1

• concreting the vertical elements of floors 5-6;

• concreting the floor slab above the 5th floor;

• bricklaying the walls and partitions on the 1st floor and in the basement;

• vertical waterproofing of the basement walls.

Sections 2

• installation of a screed on floors 2-7;

• covering the roofing with gravel.

Section 3

• installation of cold-water and heating pipes;

• installation of a cement-sand screed on floors 6-7;

• covering the roofing with gravel.

Section 4

• running electrical power cables from the apartment distribution panels to the floor distribution panel.

Intermediate section

• concreting of reinforced concrete elements on the 2nd floor level on the terrace.

Sections 5 and 6

• plastering walls on floors 1-5 in Section 6.

Other types of work

• vertical waterproofing of underground parking lot walls.