Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%

Progress in construction RC “SHCHASLYVYI” Lviv, February 2024

The first two buildings of the residential complex have been commissioned, the construction of the third building is underway:

• installation of apartment doors (2-17 floors);

• tiling the floor in the public usage places (10-11 floors);

• preparatory works for installation of the suspended ceiling "Armstrong";

• welding of gas pipes around the perimeter of the building (60% complete).