1
stage
100%

The first two buildings of the residential complex have been commissioned, the construction of the third building is underway:
• installation of apartment doors (2-17 floors);
• tiling the floor in the public usage places (10-11 floors);
• preparatory works for installation of the suspended ceiling "Armstrong";
• welding of gas pipes around the perimeter of the building (60% complete).
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: FEBRUARY 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
28.02.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (FEBRUARY 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
28.02.2026
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: FEBRUARY 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
24.02.2026