    Dear customers and everyone desiring to purchase own cozy apartment within a walking distance to the capital! Let us inform you on the latest news about the building progress of our complexes.

    Our RC “Shchaslyvyi” in Petropavlivska Borshchagivka includes 5 houses, and the first of them located at the address 10-А Lenina Str. is brought into operation already! Landscaping of the surrounding area near the building will be finished soon. The first construction phase in Petropavlivka is ready to meet its happy owners of apartments.

   Builders are ending facade works in the second construction phase at 10-B Lenina Str. The decorative plastering of the house’s entrances will soon be over too. Surrounding area is being shaped and landscaped at present. Otis elevators are being installed in the 3rd, 4th, and 5th sections. The works on the mounting of stair railings progress in all entrances of the building.

   In apartments of the third construction phase at 10-V Lenina Str. there continue preparation works for the filling of floors with cement screed and the installation of radiators. The erection of the 6th floor started at 10-G Lenina Str., and that’s the 4th construction phase so far. The foundation footing has already been placed for the building of the basement floor in the last construction phase of the “Shchaslyvyi” development in Petropavlivka at 10-D Lenina Str.

   The construction of the “Shchaslyvyi” residential development in Sofiivska Borshchagivka is on the fast track as well!

   The roof mounting is over in the house at 50 Shchaslyva Str.! They are working on the installation of sidings at the roof bottom. Works on the insulation of the building are done in sections 1 and 6 and they still continue in sections 2, 4, and 5. Along with that there continue works on the mounting of rainwater runoffs. Rehau windows have been installed in the entire house.

   90% of the apartments plastering is over, there is only the 5th floor. So it is our advice to arrange the installation of under-floor heating, because as soon as on Monday floors will be filled with cement screed. 85% of plumbing works in apartments are done. Finishing works started in entrances: walls and ceilings are plastered before painting and refinement with decorative stucco. The connection of the building to water, gas, and electricity supply, as well as to the sewerage system will begin next week.

   Roof mounting works have started in the neighboring house at 61 Shchaslyva Str. The plastering of internal walls goes on in the 3rd and 4th sections of the house. Electricity mounting works will soon be over on the 5th floor of the 1st and 4th sections; they are finished in the rest of entrances. There have begun works on the distribution of sewerage pipes to apartments. Windows will be installed in all apartments by the end of this week.

   So don’t lose the chance to be happy in your own apartment. Visit our sales offices in Petropavlivska Borshchagivka at 10-А Lenina Str. and in Sofiivska Borshchagivka at 74 Voloshkova Str. For detailed information contact us at 067-735-76-76 and 067-409-36-36.