CONSTRUCTION OF THE RC SHCHASLYVYI (LVIV): REPORT ON NOVEMBER AND PLAN FOR DECEMBER

06.12.2022

Construction of the III phase of the residential complex Shchaslyvyi, located in Bihova street, Lviv, continues at a good pace. In particular, builders performed the following works during the previous month:

•plastering works on the 2nd, 3rd, 5th, 11th floors;

•wet facade arrangement;

•ventilated facade arrangement;

•rolling of heating and cold water pipes on the 9th, 10th, 13th floors;

•arrangement of chimney caps on the roof.

In December, the masters will be engaged in:

•wet facade arrangement: mineral wool installation, its fastening and reinforcement (if weather conditions permit);

•ventilated facade arrangement: installation of composite panels and arrangement of the subsystem between the axes;

•plastering works completion (1st floor, stairwells);

•chimney covers arrangement;

•plumbing works on rolling heating and cold water pipes (if weather conditions allow);

•roof sealing works completion;

•the beginning of parapet covers on the roof arrangement.

We would like to remind you that there are currently several favorable promotional offers at the RC Shchaslyvyi (Lviv). You can find out more on the Promotions page.

Telephone number of the sales department: +380684308208.